Engineering tool

Solar pile count, steel tonnage & refusal break-even estimator

Enter MWdc, racking, profile and refusal rate. Get piles, steel tons, truckloads, rig-days and the lowest-cost foundation strategy, recalculated live.

Project inputs

MWdc · 0.5 to 250
≈ 8 ft embedment + 4 ft reveal
% of piles that refuse before design embedment
Labor rate mode
$ per pile · DTH pre-drill + grout
Total piles
–
Galvanized steel
–
Installed budget
–
Field duration
–
Recommended foundation strategy
–

3-way refusal break-even comparison

StrategyDriven + spot pre-drillHybrid zone plan100% ground screws
Installed range
$/pile (mid)
$/Wdc (mid)
vs. lowest

Carry estimate into bid request

Bid-stage screening only. Final pile section and embedment come from site borings, load tests and the project P.E.

How the estimator calculates

Pile count

Piles = MWdc × piles per MWdc. Baselines are 295 for 1P trackers, 255 for 2P trackers, 375 for fixed-tilt 2-high portrait and 410 for 4-high landscape. Real counts move between about 220 and 450 with module wattage (550–700 W+), row length and wind zone, so enter your own count when the layout is drawn.

Steel weight and truckloads

Steel = piles × total length × AISC nominal weight per foot (W6x8.5 = 8.5, W6x9 = 9.0, W6x12 = 12.0, W6x15 = 15.0, W8x10 = 10.0 lb/ft; heavy C-pile ~7.5 lb/ft). Truckloads assume 44,000 lb legal payload per flatbed. Ground screw shaft weight varies by manufacturer; the tool uses 7 lb/ft as a typical figure.

DriverValue usedBasis
Delivered steel$1.02 / $1.14 / $0.92 per lbA572 Gr 50 + A123 HDG; IRA 100% U.S. melt ~+12%; G235 pre-galv
Rig production150 piles/rig-day ÷ (1 + 2.2 × refusal)100–150/day average; 60–80/day in rock
Spread burn rate$2,750 / $3,800 per dayRig + 3–4 person crew; open shop vs. Davis-Bacon
Refusal remediation$155 per refused pile (adjustable $75–$250)Auger or DTH pre-drill + grout backfill
Ground screw installed$185/pile (≥5 MWdc), $260/pile (<5 MWdc)$120–$250 utility, $180–$400+ C&I
Hybrid zone planZones cover ~2× refused positions; $25k mob + $4/pile mappingDriven steel on clear ground, screws in mapped rock
Budget band−12% / +15% around midpointMill index, freight distance, mob

Refusal production drag

Refused holes stop the rig while the crew pre-drills, sets and grouts. The tool divides clear-soil output by (1 + 2.2 × refusal fraction). At 15% refusal that is about 113 piles per rig-day, at 35% about 85, and at 55% about 68, which matches field reports of 60–80 per day in rock.

More detail on remediation methods is on refusal & hybrid remediation, unit rates are on 2026 pricing benchmarks, and the tests that set embedment depth are on ASTM load testing.

Send the pile schedule. Get a foundation bid.

MWdc, racking, geotech status and mobilization window are enough to start. Steel supply, driving crews, ground screws, pre-drilling and load testing priced as one package or line by line.