How the estimator calculates
Pile count
Piles = MWdc × piles per MWdc. Baselines are 295 for 1P trackers, 255 for 2P trackers, 375 for fixed-tilt 2-high portrait and 410 for 4-high landscape. Real counts move between about 220 and 450 with module wattage (550–700 W+), row length and wind zone, so enter your own count when the layout is drawn.
Steel weight and truckloads
Steel = piles × total length × AISC nominal weight per foot (W6x8.5 = 8.5, W6x9 = 9.0, W6x12 = 12.0, W6x15 = 15.0, W8x10 = 10.0 lb/ft; heavy C-pile ~7.5 lb/ft). Truckloads assume 44,000 lb legal payload per flatbed. Ground screw shaft weight varies by manufacturer; the tool uses 7 lb/ft as a typical figure.
| Driver | Value used | Basis |
|---|---|---|
| Delivered steel | $1.02 / $1.14 / $0.92 per lb | A572 Gr 50 + A123 HDG; IRA 100% U.S. melt ~+12%; G235 pre-galv |
| Rig production | 150 piles/rig-day ÷ (1 + 2.2 × refusal) | 100–150/day average; 60–80/day in rock |
| Spread burn rate | $2,750 / $3,800 per day | Rig + 3–4 person crew; open shop vs. Davis-Bacon |
| Refusal remediation | $155 per refused pile (adjustable $75–$250) | Auger or DTH pre-drill + grout backfill |
| Ground screw installed | $185/pile (≥5 MWdc), $260/pile (<5 MWdc) | $120–$250 utility, $180–$400+ C&I |
| Hybrid zone plan | Zones cover ~2× refused positions; $25k mob + $4/pile mapping | Driven steel on clear ground, screws in mapped rock |
| Budget band | −12% / +15% around midpoint | Mill index, freight distance, mob |
Refusal production drag
Refused holes stop the rig while the crew pre-drills, sets and grouts. The tool divides clear-soil output by (1 + 2.2 × refusal fraction). At 15% refusal that is about 113 piles per rig-day, at 35% about 85, and at 55% about 68, which matches field reports of 60–80 per day in rock.
More detail on remediation methods is on refusal & hybrid remediation, unit rates are on 2026 pricing benchmarks, and the tests that set embedment depth are on ASTM load testing.