Pricing

2026 commercial & utility solar pile pricing benchmarks

Steel, installation, refusal and load testing ranges in one table, plus the five drivers that swing a bid.

Consolidated 2026 benchmark table

U.S. commercial and utility ranges for bid-stage budgeting. Delivered steel prices include galvanizing and punching. Installed prices include material, freight and install at normal volume, excluding refusal remediation unless stated.

Delivered galvanized steel

Item$/lb$/short tonExample
ASTM A572 Gr 50 + A123 HDG, punched$0.85–$1.25+$1,700–$2,500+10 ft W6x9 (90 lb): $77–$113
IRA 100% U.S. melted & poured+8–15% over blended—10 ft W6x15 (150 lb): $128–$188 before premium
Pre-galvanized G235 coil (C-pile)~$0.80–$1.05~$1,600–$2,100Mill and gauge dependent

Installed unit cost by foundation type

Foundation$/pile installed$/Wdc (foundation share)
W6x9 driven, 10–13 ft$105–$180$0.03–$0.05
W6x12 driven, 10–13 ft$125–$225$0.035–$0.06
W6x15 driven, 10–13 ft$150–$270$0.04–$0.075
Roll-formed C-pile, 10–13 ft$80–$150$0.02–$0.04
Ground screw, utility volume$120–$250$0.03–$0.07
Helical pile, C&I footprint$180–$400+Site-specific
$/Wdc assumes ~250–300 piles per MWdc on trackers; fixed-tilt pile counts are higher.

Driving, refusal and testing

ItemRate
Driving spread, open shop$2,300–$3,250+/day
Driving spread, prevailing wage / union$3,200–$4,400+/day
Subcontract driving labor + equipment$15–$30+/pile normal soil; $18–$35/pile W6x15
Refusal pre-drill + grout adder$75–$250+ per refused pile
Load test mobilization$3,000–$10,000+
ASTM D3689 / D3966 test$1,500–$3,500 each
Full geotech + load test campaign$15,000–$80,000+

What moves a foundation bid

  1. Steel mill index and IRA melt allocation. Steel is half or more of the driven-pile package. A 10% move in hot-rolled pricing moves the bid 5% or more, and domestic melt allocation adds 8–15%.
  2. Refusal percentage. Each refused pile adds $75–$250 and slows the rig. At 25–30% refusal, the foundation type itself can change. See refusal economics.
  3. Wind and snow embedment depth. One extra foot on 30,000 piles of W6x9 is 135 tons of steel. Load testing pays for itself here.
  4. Davis-Bacon prevailing wage. It adds roughly $900–$1,200 per spread-day over open shop.
  5. Freight distance. Flatbed haul from mill and galvanizer to site at 44,000 lb per load. Remote sites far from a galvanizer pay more per ton delivered.
Galvanized steel sections bundled for shipment
Steel is the largest single line in a driven-pile foundation package.

Put these rates to work on your layout in the pile estimator, then request a bid to replace ranges with a firm number.

Send the pile schedule. Get a foundation bid.

MWdc, racking, geotech status and mobilization window are enough to start. Steel supply, driving crews, ground screws, pre-drilling and load testing priced as one package or line by line.